Member changing rooms and Health Suite update

Member Changing rooms reopening Saturday 18th November & Health Suite reopening 25th November

We are excited to announce the reopening of our newly refurbished Member changing rooms on Saturday 18th November and Health Suite on 25th November.

Due to a delay in equipment delivery the Health Suite will be reopening the following Saturday 25th November. We thank you for your patience during these refurbishments, and hope you enjoy the improved facilities.

Refurbishments works 25th September - 25th November

There will be an information board in the reception area that will display drawings and a programme of works update. Works will include - but are not just confined to - the following:

Week 1 -Removal of existing furniture.
Week 2- Deep cleaning of wall and ceiling tiles, floor screed, floor tiles.
week 3- Deep clean of floor tiles and re grout shower, new floor tiles to changing rooms and WC area. New plinth and falls in sauna and steam room. Sauna installation.
Week 4- Alter steam room doorway, new wall tiling shower areas only.
Week 5- Sauna cladding and tiling, steam room installation make good to corridor area.
Week 6 - Install cubicles and lockers, remove spa bath, spa bath tiling.
Week 7- Reinstate showers installing new pipe work, install new ceiling tiles in all areas. Strip out old lighting and replace with new LED. Decorations, install spa bath and snagging.

Alternative changing facilities are available in the pool change and dry changing rooms. Members will also have access to The Triangle, Kings Centre* and the facilities at Pavilions in Horsham.


We apologise for any inconvenience caused and will do everything we can to minimise disruption during the works.
*Kings Centre does not have a health suite.